Is there a way to write a Quartz CronTrigger expression that runs every day between two dates, for example starts at 11am 5th of Sep 2011 and ends at 11am 10th of June 2012?

Answer

Use an expression that means every day at 11:00am e.g. “0 0 11 * * ?”.

Then set the startTime of the trigger to 5th of Sep 2011 10:59 am, and set the endTime of the trigger to 10th of June 2012 11:01 am.